Silt trap project: Update 2

After some detective work involving a number of utility companies the mystery pipe has now been identified as a redundant water main.

This was removed on Friday 17 May but means we are now behind schedule with the works. Currently the aim is that Mill Lane works will be complete by Friday 24 May and we will be ready to start on Denmark Road on Tuesday 28 May.